Customer asked us to move a wall between an existing bathroom and his bedroom to
reduce the bathroom size and increase the bedroom size. He also wanted to
upgraded the bathroom with new floor tiles, new toilet, and new shower tiles
We started with removing
the wall between bathroom and bedroom.
Then we move the bathroom
window to left to open room for the wall
Wall was placed in new
location, giving one extra foot room to the bedroom.
After moving the wall, it
was time to upgrade the bathroom.
First we removed the ugly
tile as owners put it.
We removed the tiles and
dry wall. down to an existing plastic layer.
Then we added a plastic
layer of our own.
After closing walls with
moisture resistance drywall, we filled the joints and floated the wall.
Then we tiled the shower
walls.
And installed the
fixtures.
After shower was done, we
started to tile the bathroom floor.
Picture shows how tiles
were laid under the bowl.
After tiles were laid, we
grouted and sealed them.