Clients
needed to change a storage room to a Bathroom.
1- We started with demolition
of the storage room wall .
2- We set the wall back to
the width of bathroom
3- Space gained was added to
the garage space to provide additional room for a hobby shop in garage.
Space under new bathroom floor is used for storage. Location of the water
hear show amount of set back. Water heater was relocated to under the new
bathroom.
4- Then we added plumbing
for the bathroom and connect them to the house plumbing.
5- Picture shows wall studs in place and
ready for drywall.
6- Dry walls are in place.
working on wiring
7- Picture shows the
bathroom plumbing.
8- A layer of Thinset floor
in poured. This layer of Thinset levels the floor and makes it ready
for installing tiles.
9- Floor tiles are laid.
10- Tiles are grouted,
Baseboards are placed.
11- Tiles are protected while
walls are being painted.
12- Shower floor tiles are
laid.
13- While waiting for shower
floor to dry, we set closet mirror and toilet
bowl in place. Then started on setting shower wall tiles in place.
14- Progress
15- Progress
16- Shower tiles are set
and grouted.
17- Shower door and
lavatory cabinet are installed.