Doran Construction   License No.

 819463, HIC

 
  Adding a Bathroom;

Clients needed to change a storage room to a Bathroom. 

1- We started with demolition of the storage room wall .

2- We set the wall back to the width of bathroom
3- Space gained was added to the garage space to provide additional room for a hobby shop in garage. Space under new bathroom floor is used for storage. Location of the water hear show amount of set back. Water heater was relocated to under the new bathroom.
4- Then we added plumbing for the bathroom and connect them to the house plumbing.

5- Picture shows wall studs in place and ready for drywall.

6- Dry walls are in place. working on wiring
7- Picture shows the bathroom plumbing.
8- A layer of Thinset floor in poured. This layer of Thinset levels the floor and makes it  ready for installing tiles.
9- Floor tiles are laid.
10- Tiles are grouted, Baseboards are placed.

11- Tiles are protected while walls are being painted.
12- Shower floor tiles are laid.
13- While waiting for shower floor to dry, we set closet mirror and toilet bowl in place. Then started on setting shower wall tiles in place.

14- Progress

15- Progress
16- Shower tiles are set and grouted.
17- Shower door and lavatory cabinet are installed.
18- Preparation to tile Lavatory Cabinet
19- Cabinet is tiled.
20- Lavatory and faucet are installed.