Customer had hired another contractor earlier, but after doing some demolition,
the contractor had decided that he is not able to do this project and had left
the job.
1- This is who the
kitchen looked when we started the project.
2- Step one was
demolition of the existing kitchen.
3- Demolition continues.
4- Demolition is
completed and trash is hulled.
5- Preparation has began
for tiling the floor. where old counter used to be.
6- At the same time,
cabinet maker is making the cabinets.
7- And counter tops are
made at stone shop.
8- Hard backings are
installed and floor is prepped for tiling.
9- Calculating power
requirements of the new kitchen, we realized that house old 125 amp
electrical panel is insufficient.
10- We installed a new
200 Amp panel and pulled new wires for the kitchen and reduced load of some
of house old circuits.
11- Picture shows new
wiring for the new kitchen lights.
12- At the same time, we
started laying tiles in kitchen floor.
13- Previous contractor
had change a window in kitchen and left it incomplete. we finished his work
and fixed the walls around window.
14- While tiling was
progressing, we finished repairing the walls.