Doran Construction   License No.

 819463, HIC

 
  Kitchen One; Page One

Customer had hired another contractor earlier, but after doing some demolition, the contractor had decided that he is not able to do this project and had left the job.

1- This is who the kitchen looked when we started the project.

2- Step one was demolition of the existing kitchen.

3- Demolition continues.
4- Demolition is completed and trash is hulled.

5- Preparation has began for tiling the floor. where old counter used to be.

6- At the same time, cabinet maker is making the cabinets.

7- And counter tops are made at stone shop.

8- Hard backings are installed and floor is prepped for tiling.
9- Calculating power requirements of the new kitchen, we realized that house old 125 amp electrical panel is insufficient.

10- We installed a new 200 Amp panel and pulled new wires for the kitchen and reduced load of some of house old circuits.

11- Picture shows new wiring for the new kitchen lights.
12- At the same time, we started laying tiles in kitchen floor.
13- Previous contractor had change a window in kitchen and left it incomplete. we finished his work and fixed the walls around window.
14- While tiling was progressing, we finished repairing the walls.

15- Ceiling is being repaired and textured.